RAMS and Risk Assessments: A Plain-English Guide
The email usually turns up on a Thursday. You’ve won the job, you’ve got the date in the diary, and then: “Before access can be arranged, please forward your RAMS and a copy of your public liability certificate.” No explanation, no template, and a start date on Monday.
Plenty of good trades quietly let that one go — they reply that they’ll pass on this occasion, or they just never answer. Which is exactly why it’s worth half a day of your life. The paperwork isn’t hard, it’s reusable, and the moment you can produce it you’re in the queue for work that most of your competition has written themselves out of.
General guidance, not health-and-safety advice. Your legal duties depend on the work, the site and who you employ — the HSE (hse.gov.uk) publishes free example risk assessments and guidance by trade, and that’s the place to check the detail.
What RAMS actually means
It’s two documents that normally get sent as one PDF.
The risk assessment is the thinking: what on this job could hurt someone, who could get hurt, and what you’re doing to stop it. It’s backwards-looking in style — a list of hazards with controls against them.
The method statement is the doing: how the job will run, step by step, in order, so that the controls you just listed actually happen. Isolate, prove dead, lock off, strip out, first fix, test, re-energise, hand back.
That’s the whole concept. A risk assessment on its own tells someone you’ve thought about it. A method statement on its own tells them what you’ll do. Together they tell a site manager they can let you through the door without standing over you.
When you’ll be asked for them
Rarely by a homeowner. Nearly always by someone who carries liability for a building they don’t personally occupy:
- Letting and managing agents — anything in a block, communal areas especially
- Commercial sites and principal contractors — you’ll usually also be asked for certificates, insurances and an induction before you lift a tool
- Schools, care homes, surgeries, nurseries — plus safeguarding checks and strict working hours
- Councils, housing associations and facilities managers — often with their own template they want you to fill in
- Larger domestic clients on bigger builds, where a project manager is involved
The pattern: the bigger and more cautious the client, the earlier the ask. On construction projects there are also formal duties that sit on different parties depending on the job — the HSE’s guidance on construction design and management is the place to read what applies to you rather than guessing from what someone said on site.
Why bothering is worth money
Think about what that Thursday email is really doing. It’s a filter. Everyone who can’t answer it drops out before price is even discussed — not because they’re worse at the work, but because they haven’t got a two-page document.
The work left behind that filter tends to behave better than open-market domestic jobs. The client is a business rather than a household, so the decision isn’t emotional and the haggling is lighter. The jobs repeat — an agent with a hundred flats has the same leaking stopcock every month. And it’s work that doesn’t come through paying for shared leads, which makes it a useful thing to build alongside the free channels that bring you domestic work.
You write the base document once. After that each job is twenty minutes of editing a front page.
Writing the risk assessment
Five columns, one row per hazard. Not every hazard in construction — the ones genuinely present on this job.
| Hazard | Who’s at risk | What could happen | Controls | Residual risk |
|---|---|---|---|---|
| Live electrical supply in occupied office | Operative, staff | Shock, burns, arc flash | Isolate at main switch, lock off with personal padlock, prove dead with approved voltage indicator (proved before and after), warning notice at board | Low |
| Working at height — step podium to ceiling grid | Operative | Fall, dropped tools | Podium steps only (no ladders for extended work), inspected before use, set on level floor, tools tethered or in belt, area below kept clear | Low |
| Trailing leads across walkway | Staff, visitors | Trips | Route leads against walls, rubber mat over any crossing, work area taped off and signed | Low |
| Dust from drilling masonry | Operative, nearby staff | Respiratory harm | On-tool extraction, FFP3 mask (face-fit tested), drill outside core hours where possible | Low |
| Lone working, out of hours | Operative | Delayed help after an accident | Site contact notified of arrival and departure, phone charged, check-in call agreed with [name] at finish | Low |
Three things that separate a real one from a downloaded one:
- Name the actual tasks. “Electrical work — risk of shock” is a template. “Replacing consumer unit in occupied ground-floor office, supply isolated at main switch” is a risk assessment.
- Write controls you’ll genuinely do. If it says the area will be barriered and you turn up with no barriers, you’ve handed the client a document that makes you look worse than having none.
- Include the people who aren’t you. Office staff walking past, kids at a school, the resident on the floor below. That’s usually the bit a site manager reads first.
Writing the method statement
Copy this skeleton, keep it to a page or two, and change the middle section per job:
METHOD STATEMENT
Job: Consumer unit replacement, Unit 4 ground floor
Client / site: [client], [address]
Dates & hours: [date], 07:30–16:00 (out of core hours by agreement)
Prepared by: [your name], [company], [date]
PEOPLE & COMPETENCE
[Name] — qualified electrician, [card/scheme], 2 years on similar works.
No subcontractors on this task.
ACCESS & PERMITS
Keys collected from reception. Site induction completed. Permit to work
required for isolation — to be signed by [site contact] before works start.
SEQUENCE OF WORK
1. Report to site contact, confirm isolation window and affected circuits.
2. Set up exclusion zone with barrier tape and signage; protect floor.
3. Isolate supply at main switch, lock off, prove dead (prove–test–prove).
4. Remove existing unit; make safe and label all circuits.
5. Install and terminate new unit; dress conductors; fit covers.
6. Inspect and test; complete certification.
7. Energise, confirm circuits with site contact, demonstrate RCD test.
8. Remove waste, clean down, remove barriers, sign out.
PLANT, TOOLS & EQUIPMENT
Hand tools, cordless SDS with on-tool extraction, step podium (inspected),
approved voltage indicator and proving unit, test instruments (calibrated).
MATERIALS / COSHH
No hazardous substances beyond [e.g. fire-stopping sealant] — data sheet held.
WASTE
Old unit and packaging removed from site by us; disposed of at [facility].
EMERGENCY ARRANGEMENTS
Site first aider: [name]. Nearest A&E: [hospital]. In the event of an
incident, stop work, make safe, inform [site contact], record in site log.
SIGN-OFF
Briefed to and understood by all operatives:
Name ................ Signature ................ Date ............
The sequence of work is the part people skim-read, so make it match the order you’d actually describe the job out loud. If you already write a proper scope of work on your quotes, you’ve done most of the thinking — the scope says what you’ll do and the method statement says how you’ll do it safely, in the same order.
Keep it proportionate
The common failure isn’t too little paperwork. It’s a forty-page pack downloaded off the internet that mentions scaffolding, excavations and confined spaces for a job that’s two sockets and a light. Someone will read it, ask you about the scaffold plan, and you’ll have nothing to say.
A sensible setup for a small firm:
- One base document per type of work you do — say first-fix electrical, boiler swaps, bathroom refits — holding the hazards that genuinely recur.
- A one-page job sheet on the front with this job’s address, dates, people, access arrangements and anything unusual.
- Review when the job changes. Found asbestos-looking board behind the units, or the ceiling’s now coming down? Stop, revise, re-brief. A risk assessment that doesn’t match what’s happening on site is worse than none.
- Cut anything that isn’t present. Shorter and accurate beats long and generic every time.
And brief it. The document only works if the person doing the job has read it — so if you’ve taken on a subbie or a lad, go through it with them and get the sign-off line signed. That signature is also the thing that shows you briefed them, if anyone ever asks.
Making it part of your paperwork
Treat it like your insurance certificate: something you can produce in minutes, not hunt for.
- Keep the base documents as editable files on your phone and in the cloud, not just on the laptop at home.
- Name the PDFs properly —
RAMS-Unit4-ConsumerUnit-Nov26.pdf, notdoc3.pdf. - Send them with the quote on commercial jobs, before you’re asked. It separates you from everyone the agent is also emailing.
- Attach the public liability and employers’ liability certificates in the same message — it’s the same conversation about whether you’re properly covered, and sending both at once ends it.
- If the client has their own template, use theirs. Arguing for your format on someone else’s site wins nothing.
The takeaway
RAMS are two short documents: what could go wrong and what you’re doing about it, then how the job will run step by step. Write them once per type of work, edit a front page per job, and keep them honest about what’s actually on site.
The reason to do it isn’t compliance for its own sake — it’s that a whole tier of steadier, repeatable work is gated behind a question most trades can’t answer by Monday. Get the base document written on a wet afternoon and you can answer it in twenty minutes for the rest of your career. For the detail, the free templates and the duties that apply to your work, go to hse.gov.uk rather than a template farm.